In September, the Outer Banks Voice ran a story on the Harvey Soundside Site. The photo at the top showed windsurfers riding a stiff southwest wind at the site, just off the shoreline the Town of Nags Head plans to rebuild. A short walk south, on the former Pamlico Jack's property, Dare County crews had been building pickleball courts since late July.
The two projects sit side by side on the soundside but run on different clocks. The county's courts had a projected finish date before the first slab was poured. The town's living shoreline still has no start date. The water side is also the side where the people who use it most have already changed the plans.
The soundside here belongs to several public bodies at once, and that explains most of the gap between the two schedules. The Dare County Tourism Board owns the old Pamlico Jack's site. Under an agreement the county commissioners approved in February 2026, Dare County handles permitting and construction for the courts and will run and maintain them once they're finished. The Tourism Board keeps up the property around them. The Town of Nags Head runs the shoreline project to the north, which covers about 500 feet starting at the Miller Restaurant property.
| Pickleball complex | Harvey Sound Living Shoreline | |
|---|---|---|
| Lead agency | Dare County | Town of Nags Head |
| Location | Soundside Event Site, former Pamlico Jack's property | About 500 feet north of the Miller Restaurant property |
| Money | $651,110 low bid; total costs capped at $1.13 million, split evenly between the county and the Tourism Board | A little over $1 million: $460,000 state grant plus $550,000 from the Outer Banks Visitors Bureau and the NC Land and Water Fund |
| Status in the latest public update | Site work began July 27, 2026 | Permit applications under state review |
| Projected timing | Late October or early November 2026, subject to change | No construction start date set |
Both projects cost about the same, and visitor-generated money helps pay for each one. What separates them is what has to happen before anyone can dig.
Building courts on dry land is a contracting job. In the spring, Dare County commissioners awarded the work to Barnhill Contracting Company, the lowest of four bidders at $651,110. The county said then that construction would start in the summer and finish in the fall of 2026. That schedule held. Site work started Monday, July 27, and the county's current projects page projects completion in late October or early November.
The plans call for 10 regulation courts with lighting, fencing, sidewalks, utility extensions and changes to the parking area. Lights matter most on the Outer Banks in November, when the sun sets before most people finish work.
The county's most recent posted update is dated August 4, and it says the timeline may still change. The county has not posted hours, reservation rules or fees for the new complex. The OBX Pickleball Group says it is following the Nags Head courts closely and lists a "King & Queen Grand Opening Tournament" with the date still to be announced.
Until the gates open, the county's pickleball page points players to Family Recreation Park in Kill Devil Hills. It has outdoor courts inside the tennis courts and indoor courts at the Youth Center. That page also posts a weekly schedule, which is the best place to watch for programmed play at the new site once the county adds it.
The Harvey Sound project goes into the water, so the state reviews it first. The town's project FAQ, dated August 11, 2026, says engineering design is complete and permit applications have gone to the North Carolina Division of Coastal Management and other agencies. It also says construction cannot start until every required permit has been issued. An interagency scoping meeting took place on November 21, 2025.
According to the FAQ, the steps after that come in a fixed order:
When the Outer Banks Voice reported on the project September 2, the plan was to start in late October, and the CAMA permit was still pending. The town's schedule says all four steps above have to happen in order before work begins. The town has not published a construction length or said whether the launch area will close while crews work.
The project exists because the soundside is eroding. The town's 2022 Nags Head Estuarine Management Plan estimated that 55 acres have been lost along the town's 17.5 miles of estuarine shoreline since 1949, the first year reliable shoreline maps were made. Town Manager Andy Garman told the Voice that the Harvey site "was identified as a pilot site" for putting that plan into practice. The Voice also reported that the work is meant to protect infrastructure at the Soundside Event Site, where the courts are being built. So the shoreline project is partly there to protect the courts next door.
The slow track has helped the people who use the water. The town released the plan for public comment in October 2025, and the Voice reported that concerns came in "almost immediately." One resident wrote to the paper that the hard structures could create a hazard for kitesurfers, sailors, paddleboarders, boaters and people fishing. The concern was specific. Living shorelines depend on sills, low rock structures set near the shore to break up wave energy so sand and marsh grass can build up behind them.
The town changed the layout after meeting with kiteboarders and other users. The FAQ lists the changes:
The Voice also reported that about 50 feet of planned sill closest to the launch was cut to widen the launch area for wind-sport users. Some safety concerns remained even after that change.
The town now lists access as a target outcome alongside erosion control:
"Provide and preserve continuous, structure-free launch/egress corridors for kitesurfers and other windsport users."
The rest of the design holds five offshore riprap wave attenuators and three nearshore marsh sills. The town says all of them were placed outside mapped beds of submerged aquatic vegetation. The town expects erosion to slow measurably within the first one to two years after construction.
Taken together, the two schedules point to a likely order. The courts will probably open first, possibly with the OBX Pickleball Group's grand-opening tournament. The launch corridor will likely stay as it is now until the shoreline permits are issued and a contractor is hired. After construction, launch users will find a sandy entry and a corridor with no structures in it. Northern structures will carry markers, and marsh sills south of the gazebo will sit closer to shore than first planned.
Three public notices will mark each step:
If you own a Nags Head rental near the soundside, the new courts and the redesigned launch will both change how guests use the area, and your listing copy and guest guide should say so once each one opens. Brook Sparks tracks amenity changes like these in Nags Head and Dare County and can show you how they fit into your rental strategy. Request your CB Estimate® & Owner Consultation.
Stay up to date on the latest real estate trends.
I provide expert guidance for buyers, investors, and property owners looking to maximize value in coastal real estate. By understanding each client’s goals—whether lifestyle-driven or investment-focused—I help identify properties that align with long-term success. My services also include consulting for existing owners, with strategies focused on pricing, performance optimization, and simple improvements that increase revenue and visibility year-round.